Shipping And Handling Procedures

All UCT equipment and material is normally shipped via the military transportation system and thus must conform with established regulations. Normally, equipment is shipped in lockable TRICON equip ment shelters, which measure 8 feet long by 6.5 feet wide by 8 feet high.

Personnel should be assigned the responsibility for preparing a "Pack-Out List" for the project. The standard Pack-Out List form is shown in Figure 1-4. All equipment, tools, and project specific materials that may be required must be included on the Pack-Out List. The list should be checked by maintenance personnel to ensure the availability of adequate tools and spare parts. Once the Pack-Out List is completed, it is used as a checkoff list for preparing shipping documents and tracking availability and location of equipment.